Ace Restoration and Waterproofing Incorporated ACE Restoration & Waterproofing Incorporated
shim-white
"The Concrete Restoration Experts" shim-white shim-white slogan
shim-black side_recent shim-black shim_trans

Recent Projects

Featured Projects

Naval Air Station

shim_trans
shim_trans  Summery
shim_trans
shim_trans  Objective
shim_trans
shim_trans  Project Background
shim_trans
shim_trans  Scope of Work
shim_trans
shim_trans  Bravo 25 Description
shim_trans
shim_trans  Overview
shim_trans
shim_trans  Crane Rail Removal
shim_trans
shim_trans  Loss of Transverse
 Negative Moment
 Capacity over the
 Outboard Crane Rail
shim_trans
shim_trans  Concrete Repair
 Materials
shim_trans
shim_trans  Top Deck
 Repair Procedure
shim_trans
shim_trans  Under Deck Repairs
shim_trans
shim_trans  Cathodic Protection
 System
shim_trans
shim_trans  Cathodic Protection
 System Installation
shim_trans
shim_trans  Grout Resistivity
 Measurements
shim_trans
arrow_right  Reinforcing Steel
 Lead Wire Installation
shim_trans
shim_trans  Upgrade Reinforcement
 Introduction
shim_trans
shim_trans  Analysis of Bravo-25
 Load Response
shim_trans
shim_trans  Calculation of
 Bravo 25 Resistence
shim_trans
shim_trans  Modes of Failure
shim_trans
shim_trans  Bravo 25
 Upgrade Design
shim_trans
shim_trans  Concrete Surface
 Preparation
shim_trans
shim_trans  Embedded
 Reinforcement
shim_trans
shim_trans  Wet Lay-up
 Composite Laminate
shim_trans
shim_trans  Proof Tests using
 Impact Load Method
shim_trans
shim_trans  Costs
 Acknowledgements
 References
shim_trans
Turbine Deck Load Capacity Restored


shim-black

Home > Featured Project > Pearl Harbor

Featured Project

 

Reinforcing Steel Lead Wire Installation

Connections were made to three steel reinforcing bars (rebars) near the edges of each ICCP grid area. Two connections were made to longitudinal rebars. The other connection was to a transverse rebar. The connections were checked for good continuity within the entire bottom layer of reinforcing steel. The contractor accessed the rebars by drilling a 2-inch (5 cm) diameter hole through the concrete cover. Number 12 AWG (2.7 mm diameter) copper conductor lead wires were welded to the reinforcing steel at the access holes (Figure 38).

 

The rebar lead connection access hole was grouted with Sikatop 123 Plus? (Figure 39). The rebar lead wire was routed in 1-inch (2.5 cm) conduit beginning where the wire emerged from the concrete to the edge of the area where they teed into the conduit containing the anode lead wires. At the tees, the three rebar lead wires from each area were soldered to a single Number 12 AWG (2.7 mm diameter) copper conductor that serves as a cathode bus. The bus was placed in the 2-inch PVC conduit containing the anode leads and ran to the junction boxes. All wire-to-wire connections were solder joints that were sealed watertight.

 

shim-black
shim-black shim_trans shim-black shim_trans

ACE Restoration & Waterproofing, Inc.
2940 E. Miraloma Ave.
Ste. B
Anaheim, CA 92806
714.526.7366
Fax: 714.526.7965

shim_trans
shim-black

  ACE Restoration and Waterproofing Quick Service Overview:
  Concrete repair; concrete restoration, structural upgrade, epoxy injection,
  waterproofing, and more concrete technologies in Anaheim California (CA)
  by ACE Restoration and Waterproofing.

  Concrete Repair, Concrete Restoration, Epoxy Injection, Waterproofing

http://www.acerestoration.net/

 

about | services | recent projects | news | contact | sitemap | home

shim-black
shim-black

© 2013, ACE Restoration & Waterproofing, Inc.   

shim-black